PRIVATISATION · UZBEKISTAN

The state is exiting 41 major assets

Twenty-nine share packages go to public auction with international advisers; twelve flagships go to IPO and SPO. Below: the full list with stakes and timing, the deal terms and the legal basis — checked against official texts, not summaries.

29
packages to auction
12
flagships to market
10
thermal power plants
17
sold in full, 100%
Privatisation programme · UP-70
Assets to be soldUZS 30tn
Target receiptsat least UZS 10tn
Company stakes115
Real-estate objects659
Land6 100 ha
Mineral depositsat least 30
Moratorium on creating new state-participation enterprises — until 1 January 2030, excluding defence and security.

Share packages to public auction

Annex 1 to PP-145. Sale through competitive international auction with international advisers; valuation by Big Four firms.

EnterpriseStakeholderStakeAdvisersAuction
1
Universal Mobile Systems (Mobiuz)
Telecom · ООО
Ministry of Digital Technologies100%Q2 2025Q3 2025
2
UzAuto Motors
Machinery · АО
Uzavtosanoat JSC99.7%Q4 2025Q1 2026
3
UzAuto Motors Powertrain
Machinery · АО
Uzavtosanoat JSC100%Q3 2025Q4 2025
4
Uzbekinvest Export-Import Insurance
Finance · АО
State Assets Management Agency75.24%Q2 2025Q3 2025
5
Uzagrosugurta
Finance · АО
State Assets Management Agency99.35%Q2 2025Q1 2026
6
Uzbekistan GTL
Oil & gas · ООО
Uzbekneftegaz JSC100%Q3 2025Q2 2026
7
Uzbekgidroenergokurilish
Construction · АО
Uzbekhydroenergo JSC96.7%Q2 2025Q4 2025
8
Transgazmahsuskurilish
Construction · АО
Uztransgaz JSC77.6%Q2 2025Q4 2025
9
Mahsusenergogaz
Oil & gas · АО
Uzbekneftegaz JSC41%Q2 2025Q4 2025
10
Turakurgan Thermal Power Plant
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
11
Yangi Angren Thermal Power Plant
Power generation · АО
Thermal Power Plants JSC99.6%Q2 2025Q4 2025
12
Angren Thermal Power Plant
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
13
Syrdarya Thermal Power Plant
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
14
Mubarek Combined Heat & Power
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
15
Fergana Combined Heat & Power
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
16
Tashkent Combined Heat & Power
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
17
Tashkent Thermal Power Plant
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
18
Navoi Thermal Power Plant
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
19
Takhiatash Thermal Power Plant
Power generation · АО
Thermal Power Plants JSC100%Q2 2025Q4 2025
20
Technopark
Real estate · ООО
Tashkent City Khokimiyat100%Q3 2025Q1 2026
21
Uzbek Leasing International
Finance · АО
Uzmilliybank JSC45.5%Q2 2025Q1 2026
22
Uzagroleasing
Finance · АО
State Assets Management Agency97.5%Q2 2025Q1 2026
23
Tashkent Tractor Plant
Machinery · ООО
State Assets Management Agency100%Q3 2025Q1 2026
24
Sherabad Cement Plant
Construction · ООО
Almalyk MMC JSC100%Q2 2025Q4 2025
25
Yulkurilish (road construction)
Construction · АО
State Assets Management Agency100%Q2 2025Q3 2025
26
Uzsuvkurilish (water construction)
Construction · АО
State Assets Management Agency100%Q2 2025Q3 2025
27
Shargunkumir (coal)
Mining · АО
State Assets Management Agency99.93%Q2 2025Q4 2025
28
Uzmetkombinat (steel)
Metals · АО
Ministry of Economy & Finance91%Q3 2025Q1 2026
29
Navoiazot
Chemicals · АО
Ministry of Economy & Finance75%separate scheduleseparate schedule

Timing is reproduced as written in Annex 1. The resolution dates from 21 April 2025; the actual status of any given lot should be verified separately.

Flagships to market

Annex 2 to PP-145. The state retains control and floats minority stakes on international and domestic exchanges.

Navoi Mining & Metallurgical Company

Mining · Navoi region
IPO
10–15%
state stake offered
H2 2025
announcement

National Investment Fund of Uzbekistan

Finance · Tashkent
IPO
25%
state stake offered
H1 2026
announcement
Placement jointly with Franklin Templeton Asset Management

Navoiyuran (uranium)

Mining · Navoi region
IPO
10–15%
state stake offered
H2 2026
announcement

Uzbekistan Airways

Transport · Tashkent
IPO
15–20%
state stake offered
H2 2026
announcement
Placement jointly with Franklin Templeton Asset Management

Almalyk Mining & Metallurgical Company

Mining · Tashkent region
IPO
10–15%
state stake offered
H1 2027
announcement

National Electric Grid of Uzbekistan

Power generation · Tashkent
IPO
10–20%
state stake offered
H1 2027
announcement
Placement jointly with Franklin Templeton Asset Management

Uzbektelecom

Telecom · Tashkent
SPO
10–15%
state stake offered
H2 2027
announcement
Placement jointly with Franklin Templeton Asset Management

Uzbekhydroenergo

Power generation · Tashkent
IPO
15–20%
state stake offered
H2 2027
announcement
Placement jointly with Franklin Templeton Asset Management

Regional Electric Grids

Power generation · Tashkent
IPO
20–25%
state stake offered
H1 2028
announcement
Placement jointly with Franklin Templeton Asset Management

Uztransgaz

Oil & gas · Tashkent
IPO
15–20%
state stake offered
H1 2028
announcement

Uzbekistan Airports

Transport · Tashkent
IPO
15–20%
state stake offered
H1 2028
announcement
Placement jointly with Franklin Templeton Asset Management

Hududgaztaminot (gas distribution)

Oil & gas · Tashkent
IPO
15–20%
state stake offered
H2 2028
announcement
Placement jointly with Franklin Templeton Asset Management

Deal terms

What the resolution states — and what it leaves out. The second matters more: that is what remains negotiable.

Fuel supply guarantee — before the auction

Thermal plant auctions are announced "on the basis of a Ministry of Energy guarantee on fuel supply volumes" (cl. 4a). The guarantee must exist before the auction itself.

However, gas supply terms are developed "based on production and delivery capacity". The guarantee is conditional on gas being available — a material caveat in a country with winter shortfalls.

Guaranteed power offtake — before signing

The KPMG-drafted privatisation strategy provides for "guaranteed purchase of generated electricity by the principal offtaker". Terms are to be developed and agreed "before the sale and purchase agreement is signed".

Volume, tariff, price formula and term are not fixed in the decree — they belong to the contract. The offtaker is not named; Uzenergosotish JSC appears among responsible parties.

No modernisation obligation on the buyer

Plants are sold "by portfolio method based on their technical condition" — wear is priced into the lots rather than converted into an investor obligation.

By contrast, the same annex sets an Investment Agreement with explicit "investment terms" for Samarqand Avtomobil zavodi. No such clause exists for the power plants.

The model adapts to the investor

The privatisation model and schedule are developed "based on international financial market conditions, production capacity and the requirements of strategic investors" (cl. 5a).

The starting price follows a Big Four valuation; the valuation report is exempt from state expert review and serves as a reference, not a ceiling.

Right of first offer for the trustee

Where a state stake sits under trust management, it is first offered to the trustee at appraised value — and only then goes to auction.

Stakes contributed to the National Investment Fund are sold together with state shares as a single lot.

Covenants of existing loans

The State Commission reviews each listing "taking into account the financial covenants of the enterprises' current loan agreements".

An asset's debt load can move the timetable: the text provides for it directly.

The list is public. The read on a specific lot is not.

The resolution sets the frame: who sells, what stake and when. It does not answer what actually drives price — plant condition, the real scope of the fuel guarantee, covenants on existing loans, offtake terms. CAPPA assembles that picture for a specific asset and takes it into negotiation.